Demolition work by Graham and sons.
Contractual agreement was early October 2014. Waited for permit etc took weeks. The process of getting the work to start and actual bulldozing commenced around 17/11/2014.
Site leveled and hard waste removed and cleared week ending 12/12/2014. There were still grass closer to the front of the site which was picked up by builder. He also complained about grass along the fenceline and at back. Graham did the honourable thing of clearing and scrapped it out again. It was pretty much "cleared of vegetation" ready for the build job to begin. Unfortunately.. days turned into weeks and the grass started to grow back again.
The completed job.
The grass started growing back as can seen after a just a week of sunshine and showers.
After discussion with the builder, it was accepted that he will remove any required top soil that contained the grass and prepare for the slab box. This is what I call site prep and the responsibility of the builder.