The build was well under way at the beginning of week 9 Feb 2015.
Check out the photos to see with where things are at.
Units 2 and 1 slabs as well as garage footings completed on Friday 20/2/2015.
Units 2 and 3 garage footings can be seen here.
Units 3 and 4 have been boxed and meshed ready for concrete pour.
Water was leaking from the original house water pipe connected to the mains that wasn't capped off. It's the responsibility of the builder to do so and not the Demolition contractor.
Have originally requested he get the plumber in to do so at the beginning of February 2015 but obviously didn't so have firmly requested again over weekend on 21/2/2015.
Footings for unit 4 garage. Trenches dugged out right against the fenceline. Today 23/2/2015 was raining and wonder if the fence is still holding up.